1.Highlander, Inc. is implementing a project with some measurements shown in the following table:

Activity PV ($M) EV ($M) AC ($M)
A 9,200 10,000 9,700
B 23,000 20,000 18,000
C 12,000 13,000 11,000
D 8,000 10,000 12,000
E 10,000 12,000 13,000
F 7,000 9,000 10,000
G 8,000 9,000 10,000

a. Which activity is ahead of schedule and under cost?

b. Which activity is most over budget?

c. Which activity has the greatest schedule variance?

d. Which activity is on schedule with the least cost variance?

Respond to questions a-d. You should have a total of 4 answers.