Posted: September 16th, 2017
Take Test: Exam 2 Fall 2014
Content
Top of Form
Instructions
Question 1
House CompanyHouse Company adds material at the start of production. The following production information is available for June:
Beginning Work in Process Inventory
(45% complete as to conversion) 10,000 units
Started this period 120,000 units
Ending Work in Process Inventory
(80% complete as to conversion) 8,200 units
Beginning Work in Process Inventory Costs:
Material $24,500
Conversion 68,905
Current Period Costs:
Material $ 75,600
Conversion 130,053
Refer to House Company. What are the equivalent units for conversion using the weighted average method?
a. 128,360
b. 120,000
c. 130,000
d. 123,440
3 points
Question 2
House CompanyHouse Company adds material at the start of production. The following production information is available for June:
Beginning Work in Process Inventory
(45% complete as to conversion) 10,000 units
Started this period 120,000 units
Ending Work in Process Inventory
(80% complete as to conversion) 8,200 units
Beginning Work in Process Inventory Costs:
Material $24,500
Conversion 68,905
Current Period Costs:
Material $ 75,600
Conversion 130,053
Refer to House Company. What is the conversion cost per equivalent unit using the weighted average method?
a. $1.01
b. $1.05
c. $1.61
d. $1.55
Question 3
House CompanyHouse Company adds material at the start of production. The following production information is available for June:
Beginning Work in Process Inventory
(45% complete as to conversion) 10,000 units
Started this period 120,000 units
Ending Work in Process Inventory
(80% complete as to conversion) 8,200 units
Beginning Work in Process Inventory Costs:
Material $24,500
Conversion 68,905
Current Period Costs:
Material $ 75,600
Conversion 130,053
Refer to House Company. What is the material cost per equivalent unit using the weighted average method?
a. $.62
b. $.82
c. $.58
d. $.77
Question 4
Allen ManufacturingThe following March information is available for Allen Manufacturing Company when it produced 2,100 units:
Standard:
Material 2 pounds per unit @ $5.80 per pound
Labor 3 direct labor hours per unit @ $10.00 per hour
Actual:
Material 4,250 pounds purchased and used @ $5.65 per pound
Labor 6,300 direct labor hours at $9.75 per hour
Refer to Allen Manufacturing. What is the labor efficiency variance?
a. $731.25 F
b. $731.25 U
c. $750.00 F
d. $0
Question 5
In a process costing system, the journal entry to record the transfer of goods from Department #2 to Finished Goods Inventory is a
a. debit Finished Goods Inventory, credit Work in Process Inventory #2.
b. debit Work in Process Inventory #2, credit Finished Goods Inventory.
c. debit Cost of Goods Sold, credit Work in Process Inventory #2.
d. debit Finished Goods Inventory, credit Work in Process Inventory #1.
3 points
Question 6
Equivalent units of production are equal to the
a. units completed by a production department in the period.
b. identifiable units existing at the end of the period in a production department.
c. number of units worked on during the period by a production department.
d. number of whole units that could have been completed if all work of the period had been used to produce whole units.
3 points
Question 7
Transferred-in cost represents the cost from
a. the last department only.
b. the current period only.
c. the last production cycle.
d. all prior departments.
3 points
Question 8
Allen ManufacturingThe following March information is available for Allen Manufacturing Company when it produced 2,100 units:
Standard:
Material 2 pounds per unit @ $5.80 per pound
Labor 3 direct labor hours per unit @ $10.00 per hour
Actual:
Material 4,250 pounds purchased and used @ $5.65 per pound
Labor 6,300 direct labor hours at $9.75 per hour
Refer to Allen Manufacturing. What is the material price variance?
a. $637.50 U
b. $637.50 F
c. $630.00 U
d. $630.00 F
Question 9
Allen ManufacturingThe following March information is available for Allen Manufacturing Company when it produced 2,100 units:
Standard:
Material 2 pounds per unit @ $5.80 per pound
Labor 3 direct labor hours per unit @ $10.00 per hour
Actual:
Material 4,250 pounds purchased and used @ $5.65 per pound
Labor 6,300 direct labor hours at $9.75 per hour
Refer to Allen Manufacturing. What is the material quantity variance?
a. $290 F
b. $290 U
c. $275 U
d. $275 F
3 points
Question 10
The term “standard hours allowed” measures
a. actual output at actual hours.
b. actual output at standard hours.
c. budgeted output at standard hours.
d. budgeted output at actual hours.
3 points
Question 11
Which of the following factors should not be considered when deciding whether to investigate a variance?
a. likelihood that an investigation will reduce or eliminate future occurrences of the variance
b. trend of the variances over time
c. magnitude of the variance
d. whether the variance is favorable or unfavorable
3 points
Question 12
Seegar CompanySeegar Company uses a standard cost system for its production process and applies overhead based on direct labor hours. The following information is available for August when Seegar made 4,500 units:
Standard:
DLH per unit 2.50
Variable overhead per DLH $1.75
Fixed overhead per DLH $3.10
Budgeted variable overhead $21,875
Budgeted fixed overhead $38,750
Actual:
Direct labor hours 10,000
Variable overhead $26,250
Fixed overhead $38,000
Refer to Seegar Company. Using the four-variance approach, what is the variable overhead spending variance?
a. $4,375.00 U
b. $4,375.00 F
c. $8,750.00 U
d. $6,562.50 U
Question 13
Seegar CompanySeegar Company uses a standard cost system for its production process and applies overhead based on direct labor hours. The following information is available for August when Seegar made 4,500 units:
Standard:
DLH per unit 2.50
Variable overhead per DLH $1.75
Fixed overhead per DLH $3.10
Budgeted variable overhead $21,875
Budgeted fixed overhead $38,750
Actual:
Direct labor hours 10,000
Variable overhead $26,250
Fixed overhead $38,000
Refer to Seegar Company. Using the four-variance approach, what is the variable overhead efficiency variance?
a. $2,187.50 U
b. $9,937.50 F
c. $2,937.50 F
d. $2,187.50 F
Question 14
Seegar CompanySeegar Company uses a standard cost system for its production process and applies overhead based on direct labor hours. The following information is available for August when Seegar made 4,500 units:
Standard:
DLH per unit 2.50
Variable overhead per DLH $1.75
Fixed overhead per DLH $3.10
Budgeted variable overhead $21,875
Budgeted fixed overhead $38,750
Actual:
Direct labor hours 10,000
Variable overhead $26,250
Fixed overhead $38,000
Refer to Seegar Company. Using the four-variance approach, what is the fixed overhead spending variance?
a. $ 750.00 F
b. $3,125.00 F
c. $ 750.00 U
d. $7,000.00 U
Question 15
Seegar CompanySeegar Company uses a standard cost system for its production process and applies overhead based on direct labor hours. The following information is available for August when Seegar made 4,500 units:
Standard:
DLH per unit 2.50
Variable overhead per DLH $1.75
Fixed overhead per DLH $3.10
Budgeted variable overhead $21,875
Budgeted fixed overhead $38,750
Actual:
Direct labor hours 10,000
Variable overhead $26,250
Fixed overhead $38,000
Refer to Seegar Company. Using the four-variance approach, what is the fixed overhead volume variance?
a. $3,875.00 U
b. $3,125.00 F
c. $3,875.00 F
d. $6,063.00 U
Question 16
Allen ManufacturingThe following March information is available for Allen Manufacturing Company when it produced 2,100 units:
Standard:
Material 2 pounds per unit @ $5.80 per pound
Labor 3 direct labor hours per unit @ $10.00 per hour
Actual:
Material 4,250 pounds purchased and used @ $5.65 per pound
Labor 6,300 direct labor hours at $9.75 per hour
Refer to Allen Manufacturing. What is the labor rate variance?
a. $1,575 F
b. $1,594 U
c. $0
d. $1,575 U
Question 17
The Western Corporation, began operations on October 1. It employs a job-order costing system. Overhead is charged at a normal rate of $2.40 per direct labor hour. The actual operations for the month of October are summarized as follows:
a. Purchases of raw material, 33,000 pieces @ $1.40/piece.
b. Material and labor costs charged to production:
Job No.
Units
Material Directlabor cost Directlabor hours
101 10,000 $5,000 $6,000 3,000
102 8,800 3,600 5,400 2,700
103 16,000 7,000 9,000 4,500
104 8,000 3,200 4,800 2,400
105 20,000 8,000 3,600 1,800
c. Actual overhead costs incurred:
Variable $18,500
Fixed 15,000
d. Completed jobs: 101, 102, 103, and 104
e. Sales-$105,000. All units produced on Jobs 101 and 103 were sold.
Required: Compute the following $ balances on October 31:
a. Material inventory =
b. Work in process inventory
c. Finished goods inventory
d. Cost of goods sold (before closing OH)
e. Under- or overapplied overhead
Question 18
Discuss why standards may need to be changed after they have been in effect for some period of time.
Question 19
Compare and contrast job-order and process costing systems.
Place an order in 3 easy steps. Takes less than 5 mins.