11. A small consulting group of a computer systems department has seven projects to complete. How should the projects be scheduled? The time in days and project deadlines are provided below. Determine the average processing time and average tardiness for each sequencing approach: First come, first served (FCFS), shortest processing time (SPT), and earliest due date (EDD). You may wish to use the spreadsheet in FCFS SPT EDD file.
Project Time Deadline
A 8 17
B 4 25
C 12 60
D 7 51
E 10 31
F 15 29
G 18 46
H 16 39