Posted: September 16th, 2015
Project Man.
Following are data reporting progress on a project. Work on all tasks contained in the table is scheduled to be complete as of the day of the report.
|
Budget |
Begun? |
Complete? |
Actual cost |
Earned Value |
Task A |
3,100 |
Yes |
Yes |
3,100 |
|
Task B |
4,000 |
Yes |
Yes |
4,500 |
|
Task C |
2,500 |
Yes |
Yes |
2,250 |
|
Task D |
4,000 |
Yes |
No |
3,500 |
|
Task E |
3,500 |
Yes |
Yes |
4,000 |
|
Task F |
2,500 |
No |
No |
0 |
|
- Using the 50-50 Rule, what is earned value for this project?
- Using the 0-100 Rule, what is earned value for this project?
- Note the discrepancy of earned value figures when using the 50-50 Rule and 0-100 Rule. Why is there a discrepancy? Which Rule should we use? Explain your rationale.
- Using the 50-50 Rule earned value computation, what is schedule variance for the project as reported?
- What is the schedule performance index (SPI)?
- Using the 50-50 Rule earned value computation, what is the cost variance for the project as reported?
- What is the cost performance index (CPI)?
- If the total budget for this project is 50,000, use CPI to compute estimate at complete (EAC).
- Using the earned value information garnered from the above table, provide your boss a brief status report on project progress to date. Also, provide projections for future status.
Looking for the best essay writer? Click below to have a customized paper written as per your requirements.