Posted: September 16th, 2017

Project management

Project management

Order Description

Assessment Type: Course Work – individual assignment
ASSIGNMENT 1 – Coursework
ANSWER ALL QUESTIONS
2,000 Word Limit

General instructions for all assignments:
• Prepare the assignment in a word processor document to upload on to the portal.
• Your name and student number should be included in the footer of each page of the assignment document, and all pages should be numbered.
• Start each question (if there are many) on a new page in the document and provide a heading for each question. Paginate your document so that it is neatly presented.
• The assignment must be submitted on or before the due date specified by the college. There are penalties for late submissions.
• Collusion and copying are not allowed. Each assignment must be done entirely by you. There are severe penalties for copying and collusion including loss of marks in the assignment, failing the entire subject or dismissal from the course.
• Outside materials may be used in assignments but all such material must be quoted and referenced if included verbatim. In general you should present your ideas and understanding in your own words.
• All written or essay type questions in this assignment are to be answered in writing using a word processor. Use a proportionally spaced font such as Times Roman 12 point for normal, essay-type written answers.
• Referencing: Harvard Style

1. Table 1 indicates the sequence and interdependence of the 13 activities (A – N) which together are required to develop a bespoke system. The durations (in weeks) of each of the activities are given in the table
Table 1
Activity Description Duration (wks) Precedence
A Requirement Gathering 4 –
B Task Allocation 3 –
C Business Analysis 5 A
D Systems Analysis 2 –
E Unit Test 4 A
F Coding 4 C.,B,G
G Systems Testing 8 D
H Cosmetic System Change 7 D
J User Acceptance Testing 7 E
K Implementation Planning 2 J,F
L Resource Allocation 3 H
M Implementation 5 K,L
N Handover 4 M

(a) Construct a network diagram identifying the following: LO1
i. Earliest Start Time (EST)
ii. Latest Finish Time (LFT)
iii. Total Float on each activities
iv. Critical Path for the project (40 marks)

b) Assume that there is a delay of 6 weeks in completing activity G. Analyse one action that the Project Manager could take to avoid exceeding the current length of the critical path. (30 marks)
LO2
2. Evaluate five Risks associated with this project and suggest actions to manage these risks
(30 marks)
LO3, LO4

Expert paper writers are just a few clicks away

Place an order in 3 easy steps. Takes less than 5 mins.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Live Chat+1-631-333-0101EmailWhatsApp