Posted: December 22nd, 2014

Project Management

Project Management

1. Critically assess the procedures and systems necessary for successful project management
2. Apply the technical and commercial knowledge and skills to manage a project successfully
3. Appraise the importance of people management and team work
4. Evaluate the role of financial accounting and control in the profitable management of projects

This is an  assignment. You can discuss your thoughts with others but under no circumstances should you submit even a small section of the same work. If submitted work

is copied, all parties involved will be penalised.
The assignment is in three parts. The first two parts require you to apply your knowledge from the lecture material and from your background reading to write short

project management reports on the value of Scope Statements and on methods of estimating. You must show evidence of having consulted the literature and texts for

project management and reference your work appropriately. You are expected to have consulted the recommended textbooks for the module and at least five other recent

sources.
The final part requires you to use Microsoft Project Management or equivalent project management software to plan and present a brief report based around specific

planning questions.

The Electromax Project

The Parc Company makes high quality electric mopeds. Sales representatives have reported a growing demand for a racing scooter. The Managing Director (MD), Robert

Parc, is keen to exploit this emerging market. He has appointed you as Project Manager. The project is to be called Electromax.

Part 1 ? Defining the Project

1. Discuss the importance of having a complete scope statement to the success of projects. Using the Electromax project, produce a complete scope statement.
15 marks
2. Discuss how a communication plan benefits the management of projects. Demonstrate your answer by developing a communication plan for the Electromax project.
15 marks

Part 2 ? Estimating

3. The Managing Director has also requested a report on estimating techniques. He needs to know what estimating techniques exist and which is the most suitable

technique for the Electromax project.
15 Marks
4. Apply your recommended technique to the Electromax project using the information provided in Part 3.
15 Marks
Part 3 ? Planning

Table 1 gives information on the activities identified by the project team, including best estimates of duration and effort and Table 2 gives staff costs.
Following a planning workshop, the following dependencies have been identified:
 Market Analysis must await the Project Approval Meeting. Product Design and Manufacturing Study can start once Market Analysis has been completed. Product

Design Selection must not start until Product Design and Manufacturing Study have been completed.
 Detailed Marketing Plans, Manufacturing Process Specification and Detailed Product Design must not start until the Product Design Selection has been

completed. Test Prototype can start once Detailed Product Design has been completed.
 Finalise Product Design can start once Manufacturing Process Specification and Test Prototype have been completed.
 Order Components and Order Production Equipment must await the completion of Finalise Product Design. Install Production Equipment must not start until 20

days after Order Components has been completed and 40 days after Order Production Equipment has been completed.
 The Review Meeting can take place as soon as Detailed Marketing Plans and Install Production Equipment have been completed.

Activity id Activity Name Duration Effort
A Project Approved Meeting 0
B Market Analysis 25 days Marketing Manager
C Product Design 40 days Designer
D Manufacturing Study 20 days Operations Manager
E Product Design Selection 10 days Operations Manager, Designer (20% of his time i.e. one day each week)
F Detailed Marketing Plans 15 days Marketing Manager, Managing Director (10% of MD?s time approximately)
G Manufacturing Process Specification 45 days Operations Manager
2 Clerical Officers
H Detailed Product Design 40 days Designer, 1 Clerical Officer
I Test Prototype 10 days Prototype Tool
J Finalise Product Design 25 days Designer, Operations Manager (20% of Operations Manager?s time i.e. 1 day each week)
K Order Components 7 days 1 Clerical Officer
L Order Production Equipment 14 days 2 Clerical Officers
M Install Production Equipment 25 days 2 Production Engineers
N Review Meeting 1 day Designer, Operations Manager, Marketing Manager, Managing Director (Mr Parc)
Table 1: Activities, Tasks, Duration and Effort

Staff Rate per hour (?)
Marketing Manager 100.00
Designer 80.00
Operations Manager 75.00
Managing Director (Mr Parc) 200.00
Clerical Officer 50.00
Prototype Tool ?1500.00 fixed cost per use
Production Engineer 90.00
Table 2: Staffing Costs

The following points were noted during the workshop
1. The project team works an eight-hour day, Monday through to Friday
2. No work takes place on British bank holidays
3. The project starting date is 14th January 2013
4. The MD, Mr Parc is used to reading reports but expects them to be focussed and summarised. He is not familiar with Project Management terminology
5. All resources are available when required

Write a brief report, which should include some analysis, to inform the Managing Director (MD) of the following project products and events. You should summarise the

information as you feel appropriate. You should use software generated graphs and charts, including a Gantt chart, to illustrate your answers where appropriate. You

are expected to use appendices and to ensure that your graphs are easy to read and clear. Marks will be allocated for clarity, simplicity and succinctness.

Mr Parc will like to be able to see:

5. A Work Breakdown Structure.
5 marks

6. Estimates of completion dates of the tasks and of the overall project.
5 marks

7. A summary of the cost of the project, broken down into sections, including total costs.
8 marks

8. The critical path for the project.
4 marks

9. You have been alerted to the possibility that the estimated durations for the tasks E, F, G, H, J and N in Table 1 above may need to be increased by 5 days in each

case. Comment on the implications of these delays for the estimated completion date.

10. There is also a possibility that, following the Test Prototype activity that a second prototype will need to be developed before we finalise the product design.

The second prototype should be ready tested within 10 days. You are expected to report on the implications of requiring a second prototype.

You should avoid making any additional assumptions. Instead, you should ask the user for clarifications.

PLACE THIS ORDER OR A SIMILAR ORDER WITH US TODAY AND GET AN AMAZING DISCOUNT 🙂

Expert paper writers are just a few clicks away

Place an order in 3 easy steps. Takes less than 5 mins.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Live Chat+1-631-333-0101EmailWhatsApp