January 5, 2000. Conrad submitted a request for equitable adjustment

Proposed Equitable Adjustment
Material 95,000 yards@ $10/yard $950,000
Material Overhead 5% of material Cost $ 47,500
Other Direct Cost Estimation of cost impact of $ 500
the change ________

Total Manufacturing $998,000
Cost
G&A Expense 10% of Total Mfg Cost $ 99,800
_________
Total Cost $1,097,800
Profit 15% of Total Cost $ 164,670
_________
Requested Adjustment $1,262,470

February 1, 2000. The Contracting Officer requested assistance from the ACO cognizant auditor and technical personnel.

February 28, 2000. Technical personnel found that:

? Conrad purchased a reasonable amount of material.
? The proposed Material Overhead was excessive for the effort involved, issuing and administering a single purchase order. Estimated actual cost was $250.

February 28, 2000. The cognizant auditor did not question any of the proposed cost. The auditor did comment that the proposed indirect rates complied with the current Forward Pricing Rate Agreement (FPRA)

March 5, 2000. The contracting officer developed a negotiation position based on the audit and technical reports.

Equitable Adjustment Negotiation Objective

Material Accepted Conrad proposed amount $ 950,000
Material Overhead Accepted Technical recommentation $ 250
Other Direct Cost Accepted Conrad Proposed amount $ 500
________
Total Mfg Cost $ 950,750
G&A Expense Accepted proposed 10% rate $ 95,075
Total Cost $1,045,825
_________
Profit 5% of Total Cost because costs all
incurred $ 52,291
_________
Adjustment objective $1,098,116

March 31, 2000. After weeks of negotiation, the contracting officer and the contractor could not reach agreement on an equitable adjustment. The major areas of difference were Material Overhead and Profit. As a result, the contractor submitted a claim seeking payment under the disputes clause of the contract. (See attached file for data)

Expert paper writers are just a few clicks away

Place an order in 3 easy steps. Takes less than 5 mins.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00
Live Chat+1-631-333-0101EmailWhatsApp