Section A: Defining a Project Plan
Question 1:
As the main stakeholder, ITS holds the ultimate responsibility of this project. The management has assigned the following internal staff to form a project team for the IBIS project.
Your team drafted the initial list of activities in Table 3.
Table 3: Activity List for Interactive Bus Information System (IBIS) Project | |||
Activity Number | Description | Prede-cessors | Duration (days) |
1 | IBIS Project | ||
2 | Assemble project team and subcontractor | 3 | |
3 | Study user requirement | 2 | 15 |
4 | Design application software | 3 | 18 |
5 | Purchase Panel | 3 | 15 |
6 | Purchase network equipment | 3 | 10 |
7 | Site survey | 2 | 3 |
8 | Apply permit | 7 | 10 |
9 | Flooring work | 8 | 5 |
10 | Electrical cabling work | 9 | 5 |
11 | Lay Network Cables | 10 | 3 |
12 | Install network equipment | 6,11 | 2 |
13 | Install panel | 5,12 | 2 |
14 | Install Application software | 4,13 | 2 |
15 | Application software testing | 14 | 3 |
16 | Overall System Testing | 15 | 5 |
17 | Performance monitoring | 16 | 5 |
18 | Prepare system documentation | 16 | 3 |
19 | Launch IBIS | 17,18 | 1 |
Note:
You are required to:
(9 marks)
(6 marks)
Question 2:
Develop a Gantt Chart for the project based on Table 3: Activity List for IBIS Project. You shall show the columns for Activities, Duration, Start Date, Finish Date and Predecessor and the Gantt Chart.
Determine the project duration, completion date and list the activities on the critical path.
Note: There is no need to group the activities by WBS in developing this Gantt Chart. You are to use Microsoft Project to work out and present the Gantt Chart. Any other format presented will results in mark reduction. You have to show the Gantt Chart on the report instead of referring the marker to an embedded file.
Section B: Managing Project Risk
Question 1:
Note: For ease of presentation, use landscape mode for your answer
(a) Evaluatethree (3) potential risks, one from each category of: External, Organisational and Project Management, by designing a Risk Assessment Matrix. You shall present your answer in the format of Table 4 shown below.
Use rating of 0 to 5 for Likelihood, Impact and Detection Difficulty.
Likelihood: 0 – Not likely to happen at all; 5 – very likely to happen
Impact: 0- No impact on project; 5 – very high impact on project
Detection Difficulty – 0 – very easy to be detected; 5 – impossible to be detected.
Table 4: Risk Assessment Matrix | ||||||
Risk (Category stated. You have to describe the risk) | Con-sequence | Like-lihood (L) | Impact (I) | Detect
-tion Difficulty (D) |
Risk Value, R=LxIxD | Comment on the risk and its risk value |
External: | ||||||
Organisational: | ||||||
Project Management: |
You shall present your answer in the format of Table 5
Table 5: Risk Response Plan Risk identified in Q 7(a) | Response | Contingency Plan | Tigger | Who is responsible |
External: Risk 1 | ||||
Organisational: Risk 2 | ||||
Project Management: Risk 3 |
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more