Posted: October 19th, 2016
Question 2 The following table provides information on a container terminal’s activities, immediate predecessor activities and their expected duration. Activity Intermediate predecessor activity Expected duration (days) Start – 0 A Start 1 B Start 3 C A 1 D A 4 E C, D 5 F D 1 G B 3 FINISH E, F, G 0 Based on the information given above, answer the following questions. a Work out the path diagram. For each activity in the path diagram, show the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and Duration (D), in the order as shown in the below table. ES= EF= Activity LS= D= LF= [10 marks] b Identify the Critical Path for the above activities. Comment on the Critical Path. [5 mark